Scope of work
- Replace nozzles on two vessels.
- Welded internal clips and supports.
- Welded internal tower attachments for demister and diffuser.
Photographs
Approved project photography: [Content required from IES]
Project overview
- Man-hours
- 4,299
- Craftsmen
- 18
- Work schedule
- 1x12x7
- Duration
- 29 days
- Location
- [Required from IES]
- Service
- Specialty Welding & Mechanical