Scope of work
- Deethanizer 14' x 16' I.D.: install (44) 4-pass trays & seal weld (3) chimney trays.
- Debutanizer 9'-6" I.D.: install (36) 2-pass trays.
- Butane splitter 12' I.D.: install (90) 2 & 4 pass trays.
- Amine contactor 7' I.D.: install (20) 1-pass trays & seal weld (1) chimney tray.
- Glycol contactor 5' I.D.: install (22) layers of structured packing & seal weld (1) chimney tray.
- Spent caustic degassing drum 3' I.D.: tray installation.
- Tray inspection: depropanizer 13' I.D., amine still 3'-6" I.D., Merox isobutane extractor plus 5' I.D., Merox normal butane extractor plus 7' I.D.
Photographs
Approved project photography: [Content required from IES]
Project overview
- Man-hours
- 17,763
- Craftsmen
- 50
- Work schedule
- 1x12x7
- Duration
- 80 days
- Location
- [Required from IES]
- Service
- Towers, Reactors & Vessel Internals