Scope of work
- Depropanizer 13' I.D.: install (42) 4-pass trays.
- Iso extractor plus 5' I.D.: seal weld (7) trays.
- Normal extractor plus 7' I.D.: seal weld (8) trays.
Photographs
Approved project photography: [Content required from IES]
Project overview
- Man-hours
- 2,065
- Craftsmen
- 11
- Work schedule
- 1x10x6
- Duration
- 32 days
- Location
- [Required from IES]
- Service
- Fabrication & Installation