2019 · Targa Resources

Train 7 — Field Installation & Tray Inspection

Scope of work

  • Deethanizer 14' x 16' I.D.: install (44) 4-pass trays & seal weld (3) chimney trays.
  • Debutanizer 9'-6" I.D.: install (36) 2-pass trays.
  • Butane splitter 12' I.D.: install (90) 2 & 4 pass trays.
  • Amine contactor 7' I.D.: install (20) 1-pass trays & seal weld (1) chimney tray.
  • Glycol contactor 5' I.D.: install (22) layers of structured packing & seal weld (1) chimney tray.
  • Spent caustic degassing drum 3' I.D.: tray installation.
  • Tray inspection: depropanizer 13' I.D., amine still 3'-6" I.D., Merox isobutane extractor plus 5' I.D., Merox normal butane extractor plus 7' I.D.

Photographs

Approved project photography: [Content required from IES]

Project overview

Man-hours
17,763
Craftsmen
50
Work schedule
1x12x7
Duration
80 days