Mentone Train 3 Gas Plant: Tray Installation and Inspection
Scope of work
- Fabricate and install 2" and 3" 304ss piping per code.
Photographs
Approved project photography: [Content required from IES]
Project overview
- Man-hours
- 1,867
- Craftsmen
- 13
- Work schedule
- 1x10x7
- Duration
- 11.5 days
- Location
- [Required from IES]
- Service
- Towers, Reactors & Vessel Internals